Our process, start to finish

From your first meeting to move-in: roughly four to six months for semi-custom Kizahashi, and eight to twelve months for full-custom Atsurae. Construction itself takes about three to four months.

About four to six months for Kizahashi, eight to twelve for Atsurae from your first meeting to move-in (construction itself takes about three to four months)

The time shown for each step is for Kizahashi. Atsurae takes longer at the planning and detailed-design stages, because the plans are drawn from scratch. Consultation and estimates are free.

Before you sign

1

Site visit

We check the surrounding area, road access, and water and gas utilities at the planned site, including any legal restrictions.

1-2 daysFree
2

Needs interview

We ask in detail about your layout preferences, budget, and design ideas, and start building the plan together with you.

1-2 weeksFree
3

Preliminary estimate

We prepare an estimate alongside the layout proposal, including help with a loan application, and walk you through the schedule.

1-2 weeksFree
4

Final planning meetings

We work through the layout, fixtures, specifications, and colors, from major decisions down to the details.

2-4 weeks
Showroom visit
5

Showroom visit

You can see and choose kitchens, bathrooms, and other fixtures in person at a manufacturer's showroom.

1-2 days
6

Construction contract

Once you are satisfied with the estimate and financing plan, we sign the construction contract.

Contract payment due

Groundbreaking to move-in

7

Soil survey

We survey the building site's soil, check its type and strength, and carry out ground improvement if needed.

1-2 days
Ground-breaking ceremony
8

Ground-breaking ceremony

A traditional ceremony (jichinsai) with a Shinto priest blesses the site before construction begins.

1 day
9

Exterior and finish selections

We finalize the exterior wall, sash, and roof colors along with structural hardware, sometimes in a single meeting.

1-2 days
Framing
10

Framing

After the soil survey and building confirmation, the structural frame goes up. A small framing ceremony is optional.

About 1 month after groundbreakingInterim payment due
Construction
11

Construction

After framing, interior finishing, plumbing, and fixtures such as the kitchen and bathroom are installed.

About 2-3 months
Completion and client inspection
12

Completion and client inspection

Once the building is complete, you walk through it with us to check for any defects or issues.

1 day
13

Handover

Keys and warranty documents are handed over, and you sign to confirm the work is complete.

Final payment due
Move-in
14

Move-in

Your new life begins. We inspect the house after handover.

Contracts and the legally required disclosure statement are prepared in Japanese only.